Construction Backlog: Measuring It for a Valuation or Sale
Backlog, the work a construction company has lined up but not yet performed, has no common definition. Two dissenting members of the Financial Accounting Standards Board (FASB) noted this, and that backlog may include contracts that are only anticipated. Official rules deal instead with the contracts behind it: which signed jobs count, how much of each price remains to be earned, what financial statements disclose, and what happens to a contract in progress in a sale. This page sets out those rules, what IRS valuation guidance asks a valuer to weigh, and a schedule to prepare.
Which signed jobs count as contracts
If your company’s financial statements follow US generally accepted accounting principles (GAAP), its jobs fall under Topic 606, “Revenue from Contracts with Customers”, added by Accounting Standards Update 2014-09. Topic 606 accounts for an agreement with a customer only when all of these are true:
- the parties have approved it, in writing, orally or by their customary business practices, and are committed to perform;
- each party’s rights and the payment terms can be identified;
- it has commercial substance, meaning the risk, timing or amount of the company’s future cash flows is expected to change because of it;
- it is probable that the company will collect the amount it will be entitled to, judged only on the customer’s ability and intention to pay.
A contract is an agreement that creates enforceable rights and obligations, and whether they are enforceable is a matter of law. For Topic 606, no contract exists if each party has the unilateral enforceable right to end a wholly unperformed contract without compensating the other. A contract is wholly unperformed when both of these are true:
- the company has not yet transferred any of the promised goods or services to the customer;
- it has not yet received, and is not yet entitled to receive, any payment for them.
So a job you have been awarded is not a contract under the standard while it is wholly unperformed and each side can still walk away without compensating the other. That holds even if your own backlog list includes it.
Change orders, retainage and disputed amounts
Topic 606 calls a change in a contract’s scope or price, or both, that the parties approve a contract modification. It notes that in some industries this is described as a change order. A modification exists when the parties approve one that creates new, or changes existing, enforceable rights and obligations. The approval can be in writing, by oral agreement or implied by customary business practices.
Until a change is approved, the company keeps accounting for the existing contract. If the parties have approved a change in scope but not yet agreed the price, the company estimates the price change under the standard’s rules for variable consideration, including its limits on such estimates.
For federal income tax, a long-term contract’s total contract price under the percentage-of-completion method in Treasury Regulation § 1.460-4 is the amount the company reasonably expects to receive, including holdbacks, retainages and cost reimbursements. Under the same regulation:
- a bonus, award or incentive payment counts once the company can reasonably predict that it will be earned;
- a disputed amount counts to the extent the company can reasonably predict that the dispute will be resolved in its favor;
- pay the company expects from another agreement with the same customer, such as an exercised option or a follow-on contract, is not part of the price unless that agreement is aggregated with the contract under § 1.460-1(e).
How much of each price is still to be earned
Under the regulation’s percentage-of-completion method:
- the completion factor is the cumulative allocable contract costs incurred through the end of the tax year, divided by the estimated total allocable contract costs;
- the completion factor multiplied by the total contract price gives the contract’s cumulative gross receipts.
The part of the total contract price not yet taken into income is therefore the total contract price less those cumulative gross receipts. Section 460 of the Internal Revenue Code requires the method for long-term contracts, with exceptions. A long-term contract is one to manufacture, build, install or construct property that is not completed in the tax year it was entered into. The site’s article Commercial Contractor Sale in California: License Rules explains the method, the look-back interest and the exemption for some construction contracts.
What the financial statements show, and may leave out
For contracted work not yet performed, Topic 606 has a company disclose the “transaction price allocated to the remaining performance obligations”. Performance obligations are the contract’s promises to transfer distinct goods or services to the customer. The disclosure gives:
- the total transaction price allocated to performance obligations that are unsatisfied, or partly unsatisfied, at the end of the reporting period;
- an explanation of when that amount is expected to become revenue, in time bands or in words.
Among the provisions that limit what the statements show:
- a company that is not a public business entity, nor one of the other entities the standard names, may elect not to give this disclosure at all;
- no company has to include, in the amount it discloses, performance obligations in contracts with an original expected duration of one year or less.
So your company’s financial statements may not show the figure at all. In Accounting Standards Update 2016-20, the two dissenting FASB members wrote that this disclosure differs from backlog. Their reason was that backlog “may include, among other differences, anticipated contracts, wholly unperformed contracts, renewal options, and estimates of variable consideration that are constrained”. They added that backlog “may not be comparable across entities because there is no common definition.”
What a valuer can check is the contracts behind each line of your schedule.
Contracts in progress when the company is sold
Under § 1.460-4(k), a transaction is a mid-contract change in taxpayer when both of these are true:
- a taxpayer (the old taxpayer) accounts for a long-term contract using a long-term contract method;
- before the contract is complete, the transaction makes another taxpayer (the new taxpayer) responsible for accounting for its income.
The contract stays the same contract if its terms are not substantially changed in the transaction, whether or not the customer releases the old taxpayer from any or all of its obligations. What happens next depends on the form of the deal:
- Constructive completion, which generally includes taxable sales under section 1001 and deemed asset sales under section 338, and covers any change of taxpayer not on the step-in-the-shoes list. The old taxpayer is treated as completing the contract on the date of the transaction. Its total contract price is the amounts realized from the transaction that are allocable to the contract, plus the amounts it has received or reasonably expects to receive under the contract. Any amount it pays the new taxpayer, and any transaction costs, allocable to the contract are subtracted. The new taxpayer is treated as entering into a new contract that day. If it uses the percentage-of-completion method for that contract, its total contract price is what it reasonably expects to receive under it. That price is reduced by the consideration it paid, and the transaction costs, allocable to the contract.
- Step-in-the-shoes transactions, which the regulation lists. They include transfers under section 351, certain reorganizations, transfers of S corporation stock and most transfers of partnership interests, with special rules for S corporations and partnerships. The new taxpayer must keep accounting for the contract with the old taxpayer’s method. An old taxpayer using the percentage-of-completion method recognizes income based on the cumulative allocable contract costs incurred as of the date of the transaction.
So in a constructive completion, the part of the deal price allocable to contracts in progress enters the old taxpayer’s total contract price and reduces the new taxpayer’s. Ask your tax adviser how it will be allocated before the deal closes.
The contractor’s license is a separate question. Under Business and Professions Code section 7075.1, no California contractor’s license can be transferred to any other person or entity. The article on license rules linked above explains what that means in a sale.
Where backlog fits in a valuer’s analysis
Revenue Ruling 59-60 sets out how the IRS approaches the value of closely held stock for estate and gift tax. Its text is reproduced in Appendix A of an IRS job aid for its valuation analysts. Some of its statements bear on contracted work:
- Valuation of securities “is, in essence, a prophesy as to the future and must be based on facts available at the required date of appraisal”. So a backlog schedule should show the contracts as they stood at the valuation date.
- “Uncertainty as to the stability or continuity of the future income from a property decreases its value by increasing the risk of loss of earnings and value in the future.”
- “Prior earnings records usually are the most reliable guide as to the future expectancy”. In another passage, the ruling says past events that are unlikely to recur “should be discounted, since value has a close relation to future expectancy.”
The IRS’s business valuation guidelines (IRM 4.48.4) are written for IRS employees who value businesses or review others’ valuations. They have the appraiser set a discount or capitalization rate after considering factors that include the risk involved and the stability or irregularity of earnings.
None of these sources gives a ratio, a multiple or a premium for backlog. A contract schedule is evidence on the questions they raise: how much future income is under contract at the valuation date, how stable it is, and whether a strong recent year came from a job that will not be repeated. What this means for your business depends on its own numbers and the purpose of the valuation; that is what a valuation report sets out.
For what a valuation for a buyer’s SBA 7(a) loan must meet, and what IRS and SBA rules require of the appraiser, see Business Valuation Requirements for SBA 7(a) Loans to Buy a Business and Certified or Qualified Business Appraisers: What IRS and SBA Rules Require.
A backlog schedule a valuer can check
For each job, as of the valuation date:
- the customer, the date the contract was signed, and whether either side can still cancel it without compensating the other;
- the base contract price, approved change orders, change orders approved in scope but not yet priced, and amounts in dispute, each shown separately;
- retainage the customer is holding;
- allocable costs incurred to date and estimated total allocable costs, which give the completion factor;
- revenue reported to date, the price still to be earned, and when you expect to earn it;
- whether the contract will stay in the company or pass to a buyer in the planned deal.
Keep work you expect but have not signed, such as outstanding bids, options and follow-on contracts, on a separate list, for the reasons given above.
Frequently asked questions
Is a job we have been awarded but not started a contract?
Not under Topic 606 while it is wholly unperformed and each side can still cancel it without compensating the other. It can still appear on your own backlog list.
Must a private contractor’s financial statements show remaining performance obligations?
Not necessarily. A company that is not a public business entity, nor one of the other entities Topic 606 names, may elect not to give that disclosure.
Does retainage count in a contract’s price for tax?
Yes, for a long-term contract under the percentage-of-completion method: § 1.460-4 defines its total contract price as the amount the company reasonably expects to receive, including holdbacks, retainages and cost reimbursements.
How is a half-finished contract taxed when it changes hands in a taxable sale?
If it is a long-term contract accounted for using a long-term contract method, § 1.460-4(k) applies. Constructive completions generally include taxable sales under section 1001. They do not include the transactions on the regulation’s step-in-the-shoes list, such as a transfer of S corporation stock. In a constructive completion the seller is treated as completing the contract on the date of the transaction, and the buyer as entering into a new contract that day.
Related reading
- Commercial Contractor Sale in California: License Rules
- Insurance Agency Business Valuation in California
- SaaS Business Valuation: What IRS Valuation Rules Ask an Appraiser to Weigh
Valuing your own business? Los Angeles Business Valuations’ reports start from $799. See Services & Pricing or contact us. For a first estimate, try the free business valuation calculator.
Prefer to talk first? Book a free discovery call with Andrew Mackson or Ryan Maguire, partners at Los Angeles Business Valuations.